Conversion of Existing Railway Line Between Pamukova and Osmaneli Km: 167+660 - 203+660 to Double Track Line

Bilecik, Türkiye

Client General Directorate of Turkish State Railways (TCDD)
Partner KMG PROJE Eng. Cons. Information Tech. Ltd. Co. (Turkey)
TCDD Technical Engineering and Consulting Inc. (Turkey)
Financing Local
Duration of Services 11/2023 - Ongoing
Brief Description of the Project:

Within the scope of the project, it is planned to convert the Pamukova-Osmaneli railway into a double track in order to increase the railway transportation capacity between Ankara and Istanbul and to raise the railway standards.

For this purpose, studies are  being carried out to convert the existing single-track railway, approximately 36 km long between Sarmaşık Station and Pamukova Stations, into double-track.

Scope of Services :
  • Obtaining, examining and evaluating the current design, information and documents from the Client,
  • Examining and Evaluating the Current Topographic and Geological Maps,
  • 1/25,000 Scale Route Studies,
  • 1/25,000 Scale Triangulation, Leveling and Grid Studies,
  • Preparation of 1/1,000 Scale Maps,
  • Preparation of Geological-Geotechnical-Geophysical Survey Report,
  • Determination of Project Horizontal and Vertical Line and Preparation of Reports,
  • Preparation of Hydraulic and Hydrological Surveys,
  • Preparation of Route Superstructure Designs,
  • Preparation of Drainage Designs,
  • Preparation of Bridge Designs,
  • Preparation of Shoring and Retaining Wall Designs,
  • Preparation of Final Designs Report,
  • Preparation of Construction Works Tender Documents.