Brief Description of the Project :

TurkStream Gas Pipeline - onshore section 2 is defined in the IGA (Intergovernmental Agreement signed by the Government of the Russian Federation and the Government of the Republic of Turkey in October 2016) as the section of the TurkStream Gas Pipeline to be constructed to ensure transit of natural gas from the offshore section 2 across the Republic of Turkey to the neighboring countries of the Republic of Turkey with a route running from the first weld after the exit side fencing downstream of the Receiving Terminal (RT).

Accordingly, Project inlet point is considered the exit of Receiving Terminal in Kıyıköy (KP 0+000) and exit point is the Turkish/Bulgarian border near Malkoclar (approximately KP 142+000).

The onshore  section-2  natural  gas  pipeline  with  a  diameter  of 48" (inch)  from  Kıyıköy  to Turkish/Bulgarian border near Malkoçlar will be an approximately  142 km in length buried pipeline including all above and sub-ground facilities, i.e. pig launcher station, 5 mainline block valve stations and the SCADA/Telecom.

The services provided within the scope of the project consist of 2 phases:

  1. Preparation of 26 operating procedures for the line mentioned above  
  2. Preparation of 16 work scopes (+8 Tender Receiving Specifications) and Tender Packages documents

All documents were received by the Client and Turkish translations of the documents were provided.

Scope of Services:
  • Development of Operational Procedures,
  • Preparation of Tender Packages,
  • Site Visits,
  • Preparation of Reports.