Greater Istanbul Water Supply Project, Melen System (ru)
İstanbul
The objective of Melen System is to provide water from Melen River to Istanbul. The project cover preparation of the final design, tender documents for construction packages, assistance to tendering and construction supervision services. The Melen project is characterised by the components listed below: CP-01 Construction of Melen River Intake Weir, Melen and Cumhuriyet Pumping Station Melen Work Site Cumhuriyet Work Site CP-02 Construction of Pipeline Main Between Melen Water Reservoir and Kincilli Town Construction of 69 284 m in Ø2540 mm steel pipeline. CP-03A Construction and rehabilitation of damaged Pipeline Main between Kıncıllı - Ağva, and construction of Yeşilçay connection. Rehabilitation of 33 850 m damaged pipeline between Kıncıllı-Ağva and construction of 1 650 m in 2,5 m diameter pipeline between Ağva-İsaköy Pump Station for the connection of Yeşilçay system. CP-03B Construction of Pipeline Between Ağva – Cumhuriyet Water Treatment Plant Construction of 35 233 m length in Ø2540 diameter steel pipeline within the scope of SP3. CP-04 Construction of Pipeline Between Şile Control Center – Hamidiye Tunnel The structures which form the system are given in order in accordance with the flow direction. Şile Control Center Balancing Tank – 30 200m3 Şile – Alaçalı Tunnel Type and Capacity: circular cross section, concrete lined 38.5 m3/s Diameter and Length: 4.5 m, L= 3 764 m Yeşilvadi Conduit Type: Circular cross section, steel lined, reinforced concrete Diameter and Length: 4.5 m, L= 5 454 m Alaçalı – Ömerli Tunnel Type: Circular cross section, steel lined, reinforced concrete Diameter and Length: 4.5 m, L= 4 576 m Hamidiye Tunnel Type and Capacity: circular cross section, concrete lined 38.5 m3/s Diameter and Length: 4.5 m, L= 3 460 m Ömerli Connection Type, Diameter, Length: Circular cross section, concrete lined, 4.5 m, L= 65 m Capacity: 38.5 m3/s CP-05 Construction of Cumhuriyet Water Treatment Plant The contract include the design of plant, process, detail design of process structures, procurement of construction materials and equipment, construction and installation, commissioning of the plant and remedying the defects works within the Defects Liability Period for Cumhuriyet Water Treatment Plant CP-06 Construction of Conveyance Line Between Cumhuriyet Pumping Reservoir and Osmankuyu/ Kağithane District This section (excluding the Bosphorus Straight Crossing Tunnel) is a conveyance line which consist of 17109 m pipe line and tunnels in between Cumhuriyet Pumping reservoir and Kağıthane Distribution Centre. Afterwards, due to the revision on Ortaçeşme and Ayazağa tunnels and other tunnels and conveyance system, the length of the conveyance line increased to 20 367 m. Cumhuriyet Header Tank – Bekleme Tunnel Pipeline 5 023 m length, Ø2500 mm steel pipe. Bekleme Tunnel Type and Capacity : Circular concrete lined, 32.0 m3/s Diameter and Length: 4.5 m, L= 2 047 m Shaft Type, Depth and Diameter : Circular concrete culvert, 35 m, 8 m. Beykoz Tunnel Type and Capacity : Circular concrete lined, 32.0 m3/s Diameter and Length: 4.0 m, L= 2 843 m Beykoz – Ortaçeşme Pipeline Type and Capacity : Steel pipe, 8.3 m3/s Diameter and Length: Ø2500 mm, L= 1 330 m Ortaçeşme Tunnel Type and Capacity : Steel lined concrete, 32.0 m3/s Diameter and Length: 4.0 m, L= 966 m Ayazağa Tunnel Type and Capacity : Steel lined concrete, 32.0 m3/s Diameter and Length: 4.0 m, L= 2 826 m Osmankuyu Tunnel Type and Capacity : Steel lined concrete, 32.0 m3/s Diameter and Length: 4.0 m, L= 2 175 m Osmankuyu – Kağıthane Transmission Main Type and Capacity : Steel pipe, 8.3 m3/s Diameter and Length: 4.0 m, L= 3 035 m CP-07 Bosphorus Straight Crossing Tunnel The construction works of this section, 5 550 m, which is a part of Melen System are given as follows; Cut and cover conduit: 90.14 m (Asian side) Beykoz Shaft: 8 m inner diameters, the depth is 145 m until the base of Bosphorus tunnel Bosphorus Straight Crossing Tunnel: 4.0 m diameter, TBM for 3.1 km from European side and D&B method for 2.1 km from Asian side. Access tunnels (European side): 221 m, Bosphorus tunnel outlet All tunnels and conduits are 4.00 m diameter and steel coating between 12-20 mm thickness. CP-08 Supply of Steel Pipes and Special Parts (for SP-01 and SP-02) This contract comprise the manufacturing, testing, inner and outer isolation, transportation to site and keeping on site of 71 215 m steel pipes which will be used in Melen pressured pipeline with 2,50 m diameter and 21 mm thickness. CP-09 Supply of Steel Pipes and Special Parts (for SP-03) This contract comprise the manufacturing, testing, inner and outer isolation, transportation to site and keeping on site of 69 510 m steel pipes which will be used in SP-03 with 2,50 m diameter and 21 mm thickness. CP-10 Supply of Steel Pipes and Special Parts (for SP-06 and SP-01) This contract comprise the manufacturing, testing, inner and outer isolation, transportation to site and keeping on site of 15 867 m steel pipes which will be used in SP-06 and Cumhuriyet Pressured pipe line with 2,50 m diameter and 21 mm thickness. CP-11 Power Supply and Transmission Lines Supply, installation and construction works for Power Supply for Melen Pumping Station; 154 / 11 kV – 2 x 50 MVA Transformer Station, 9.3 km 154 kV Overhead Transmission lines, Power Supply for Cumhuriyet Pumping Station; 154 / 11 kV – 2 x 31.5 MVA Transformer Station, 12.9 km and 4.1 km, 154 kV Transmission lines.
Client
General Directorate of State Hydraulic Works (DSI)
Partners
Nippon Koei Co. Ltd. (Japan)
Sir Alexander Gibb & Partners Ltd. (UK)
Mott MacDonald Ltd. (UK)
Setan Müh. ve Müş. A.Ş. (Turkey)
Temelsu Ul. Müh. Hiz. A.Ş. (Turkey)
Sial Yer Bilimleri Ltd. Şti. (Turkey)
Financing
JBIC (Japan)
Duration of Services
1996 – 2008
Brief Description of the Project :
Scope of Services :





