Kırşehir Water Supply System Rehabilitation Project (ru)

Kırşehir

Client Municipality of Kırşehir
Partner

-

Financing World Bank (IBRD)
Duration of Services 2012 - Ongoing
Brief Description of the Project :

The Iller Bank obtained from the International Bank of Reconstruction and Development (IBRD) an additional financing (Additional Credit) to meet the cost of the “Municipal Services Project” and allocated a portion of the credit to Kırşehir Municipality for financing the “Kırşehir Drinking Water Network Project”. The scope of the project is given as follows:

  • Water network – total 134.5 km, Ø 100 – Ø 500 mm
  • Pumped main – total 3,5 km, Ø 315 – Ø 355 mm
  • Distribution Reservoir – 6 No. New reservoir (3 x 1000 m3, 2 x 2000 m3, 1 x 3000 m3)
  • Pumping Station - 43 l/s, H=60 m
  • Structures to be rehabilitated – 8 No reservoir (600 m3- 5000 m3), 4 No pumping stations
  • Establishment of SCADA system.
Scope of Services:
  • Project Management,
  • Preparation of detail design,
  • Design and establishment of SCADA system,
  • Preparation of tender documents,
  • Technical assistance during tender period and tendering,
  • Supervision of construction works,
  • Supervision of defects liability period.