SU-YAPI Engineering & Consulting Inc.

Balıkesir Water Treatment Plant

Balıkesir

Client Ataç İnşaat ve Sanayi A.Ş.
Partner -
Financing Local
Duration of Services 1998 – 2002
Brief Description of the Project :

Detail design for all process units, service structures and pumping stations for Balıkesir Potable Water Treatment system within the water supply system to satisfy the potable, domestic and industrial water demand in Balıkesir City until the year 2020

Design characteristics;

Water Treatment Plant : 220 000 m3/day capacity

Raw water pumping station P0 : Q = 1915 l/s, Hm = 88 m, total 6 units

Pumping Station P1 : Q = 342 m3/h, Hm = 52 m, total 4 units

                                         Q = 198 m3/h, Hm = 104 m, total 3 units

Pumping Station P2 : Q = 515 m3/h, Hm = 56 m, total 4 units

                                         Q = 245 m3/h, Hm = 106 m, total 2 units

Piping : Ø200 - Ø1200, spiral welded steel pipes

Reservoirs:

Clean water tank : 4 770 m3

Contact tank         : 3 180 m3

Leaching water storage tanks :   730 m3

Leaching water recycling tank : 3 000 m3

Scope of Services :
  • Preparation of preliminary design,
  • Preparation of detail design,
  • Preparation of bill of quantities and technical specifications.